Ferretti Plans Five New Ancona Halls to Double Its Metal Yachts

Ferretti Group has won a 30-year concession on the first lot of the burnt-out Tubimar site in Ancona and plans five new halls for steel and aluminium yachts of 40 to 55 metres. The first opens in 2028 and the group says the halls will double its semi-custom metal capacity. For an owner weighing a 40-to-55-metre order, that decides how many slots exist and how soon.
18 November 20264 min readYotters DeskEdited by Leon Soliman
The stern carries the name Cerulean and the home port George Town, Cayman Islands, with a folding beach-club platform built into the transom.
The stern carries the name Cerulean and the home port George Town, Cayman Islands, with a folding beach-club platform built into the transom.Photo: CRN / Ferretti Group (press material)

What exactly has Ferretti Group been given at the former Tubimar site?

Ferretti holds the concession for Lot A, 16,175 square metres of a 37,030-square-metre former industrial site in the port of Ancona, and ANSA reports the concession runs for 30 years.

The Central Adriatic Sea Port System Authority has split the old Tubimar site into four lots and is returning the whole area to shipbuilding. Ferretti took the first. Tubimar leased warehouses to storage tenants until a multi-alarm fire in September 2020 destroyed them, and the ground has sat idle since. The deal was presented on 18 November at the waterfront atelier of Ferretti's Ancona headquarters, and ANSA, Pressmare and Megayacht News all carried it the same day.

Corriere Adriatico's headline says Palumbo was also assigned part of the area, which would make Ferretti one of two yards sharing the site. We couldn't read the full piece, so treat that as a lead rather than a confirmed split. The port authority's president, Mirco Carloni, said demolition of the burnt structures starts early in the coming week, according to ANSA. Megayacht News adds that the clearance should run through spring 2027, so no hull will be built on Lot A for some time.

An aerial view of the sundeck and foredeck tender bay. Vripack drew the exterior and naval architecture, working to a brief built around diving and spearfishing rather than formal entertaining.
An aerial view of the sundeck and foredeck tender bay. Vripack drew the exterior and naval architecture, working to a brief built around diving and spearfishing rather than formal entertaining.Photo: CRN / Ferretti Group (press material)

How much will five new halls add to Ferretti's metal-yacht capacity?

Ferretti says the five halls will double its semi-custom steel and aluminium capacity, with the first opening in 2028 and the last about three years from now.

The halls target steel and aluminium yachts from 40 to 55 metres, which is the bracket the group says is seeing growing demand worldwide. They'll be built in modules, so production space comes online in stages instead of in one handover. Pressmare puts the programme at almost EUR 30m over three years. ANSA gives EUR 25m for the same project. The two outlets don't explain the gap, so the honest figure is somewhere between EUR 25m and EUR 30m until Ferretti publishes its own.

Stassi Anastassov, the group's global CEO, framed the move as a commitment to stay in Ancona and invest for the next generation, and Pressmare quotes his ambition to make the port a global centre of excellence for superyacht construction. The plan also promises solar panels, energy-efficiency systems and recycled or certified materials, following Italy's minimum environmental criteria. None of the sources gives a job count, a hall size or a model list, so what will be built in each hall is still unannounced.

Cerulean's bow, with the shallow 3.2-metre draught Vripack used to keep her close to reefs and anchorages a deeper-draught 70-metre could not reach.
Cerulean's bow, with the shallow 3.2-metre draught Vripack used to keep her close to reefs and anchorages a deeper-draught 70-metre could not reach.Photo: CRN / Ferretti Group (press material)

How does this fit with Ferretti's earlier Ancona expansion?

The five new halls are a second project: in October the port approved a EUR 3m expansion of an existing hall at the yard so it can build superyachts up to 100 metres.

Baird Maritime reported on 22 October that the port authority issued the first single authorisation under Italy's special economic zone scheme, known as ZES, to Ferretti. The approval took 54 days, covers one existing production hall and should be finished in about six months. The yard describes its full-custom steel and aluminium work as running from 45 to 95 metres, so the hall lifts the ceiling to 100.

Read together, the two projects split the yard's work by size. The existing hall chases the very large end, while the Tubimar halls add volume in the 40-to-55-metre range where the group sells semi-custom designs. Carloni told the presentation that around 20 percent of Italian-built yachts come from Ancona and that Marche shipbuilding turned over EUR 1bn in 2024 with about 4,000 employees, almost double ten years earlier. Marche exports rose 9.2 percent in the first half of 2026, against 4.5 percent nationally.

Cerulean's profile shows the navy hull and single red boot stripe CRN has used across its full-custom range.
Cerulean's profile shows the navy hull and single red boot stripe CRN has used across its full-custom range.Photo: CRN / Ferretti Group (press material)

Why is shed space in the port of Ancona being handed out now?

Ancona's yacht builders have been short of covered space for years, and the port authority is now allocating old industrial ground to shipbuilding instead of leaving it idle.

Italian trade press has run the shortage as a story since early 2025, when Superyacht24 reported that Marche yards were struggling for space, and the port followed with a plan to turn old Tubimar areas to luxury yachting. Baird Maritime notes that Fincantieri secured a concession of more than 314,000 square metres in Ancona in November 2025, which shows how much of the port is moving to ship and yacht work. Against that, Ferretti's 16,175 square metres is a mid-sized slice, and Corriere Adriatico's headline suggests the concession terms were tied to how much a yard invests, with durations reported from 4 to 30 years.

What does the yard build in that space today? Ferretti describes it as the home of CRN's full-custom steel and aluminium range, founded as a CRN shipyard in 1963 and renamed the Ferretti Group Superyacht Yard in 2019. Recent work includes the 67.55-metre hybrid Amor a Vida, delivered in May 2025, and the 70-metre Cerulean, which we covered in September after her handover three months after launch. Both sit above the 40-to-55-metre bracket the new halls target, so the Tubimar buildings add a second product line to a yard known for larger one-off boats, which is why the doubling claim applies to semi-custom metal yachts only.

Cerulean's christening at CRN's Ancona yard in June 2026, ahead of the sea trials that preceded her September delivery.
Cerulean's christening at CRN's Ancona yard in June 2026, ahead of the sea trials that preceded her September delivery.Photo: CRN / Ferretti Group (press material)
Cerulean underway. CRN's 70-metre, 1,100 GT full-custom yacht was handed to her owner on 16 September 2026, three months after launching from the Ferretti Group yard in Ancona.
Cerulean underway. CRN's 70-metre, 1,100 GT full-custom yacht was handed to her owner on 16 September 2026, three months after launching from the Ferretti Group yard in Ancona.Photo: CRN / Ferretti Group (press material)

Should a buyer of a 40-to-55-metre steel yacht care about this?

It matters mainly to buyers who want a Ferretti Group metal yacht delivered after 2028, because capacity that doesn't exist yet can't carry a contract signed today.

Nothing changes for a hull already in build. A buyer signing now still gets a slot in the current halls, and the new space is a promise with a 2028 start date. It arrives as the group's finances are under watch: Weichai took control at the May shareholder vote, order intake fell 27 percent in the first half and UBS moved to neutral. Building five halls while orders are softer is a bet that the 40-to-55-metre demand Ferretti describes returns.

So ask the yard three plain questions. Which hall and which delivery year does your slot sit in? Is any part of the price or schedule tied to the new site? And what happens to your date if the first hall slips, given that demolition hasn't finished and the concession was only just signed? The answers tell you whether you're buying existing capacity or capacity still on a drawing. Ownership is the other thing to ask about. We reported in July that Czech investor Karel Komarek took the May vote that handed Weichai control to court, and the group's leadership has changed since. A 30-year concession and a EUR 25m to EUR 30m build outlast any one board, so ask whether the delivery dates in your contract are guaranteed by the group or only by the yard, and what the contract says if the programme is cut back.

What is good, and what to watch

Strong points

  • Real ground and a real permitThe concession and the ZES route are on the record, and the port authority itself presented the deal.
  • Capacity in the right size bracket40 to 55 metres is where the semi-custom metal range sits, so the halls match what the group already sells.
  • Two projects at one yardThe 100-metre hall and the five new halls together cover both ends of the yard's size range.

What to watch

  • Nothing is built until 2028Demolition runs into spring 2027 and the first hall opens in 2028, so today's buyer gets none of this.
  • The investment figure is unsettledEUR 25m and almost EUR 30m both appear in 18 November coverage and neither source explains the difference.
  • Order intake is fallingFerretti reported a 27 percent drop in first-half order intake, so the new halls arrive ahead of proven demand.

Practical detail

Ferretti Plans Five New Ancona Halls to Double Its Metal Yachts
SiteFormer Tubimar area, port of Ancona, 37,030 sq m split into four lots
Ferretti's shareLot A, 16,175 sq m, concession reported at 30 years by ANSA
ProgrammeFive halls, built in modules, first opening 2028, last in about three years
YachtsSteel and aluminium, 40 to 55 metres, semi-custom
Stated effectDoubles the group's semi-custom metal-yacht capacity
InvestmentAlmost EUR 30m over three years (Pressmare) or EUR 25m (ANSA)
Separate projectEUR 3m hall expansion approved 21 October for yachts up to 100 m, about six months of work
What is not publishedHall sizes, job numbers, model programme and the Palumbo lot terms

Questions this story answers

What happened?

Ferretti Group has won a 30-year concession on the first lot of the burnt-out Tubimar site in Ancona and plans five new halls for steel and aluminium yachts of 40 to 55 metres. The first opens in 2028 and the group says the halls will double its semi-custom metal capacity. For an owner weighing a 40-to-55-metre order, that decides how many slots exist and how soon.

What is good about it?

Real ground and a real permit. The concession and the ZES route are on the record, and the port authority itself presented the deal.

What should an owner or buyer watch?

Nothing is built until 2028. Demolition runs into spring 2027 and the first hall opens in 2028, so today's buyer gets none of this.

Who reported this?

ANSA, 18 November 2026, Pressmare, 18 November 2026, Megayacht News, 18 November 2026, Baird Maritime, 22 October 2026, Mirco Carloni, president, Central Adriatic Sea Port System Authority, Stassi Anastassov, global CEO, Ferretti Group.

Reported from primary sources: ANSA, 18 November 2026, Pressmare, 18 November 2026, Megayacht News, 18 November 2026, Baird Maritime, 22 October 2026, Mirco Carloni, president, Central Adriatic Sea Port System Authority, Stassi Anastassov, global CEO, Ferretti Group.
Yotters DeskEditor-in-Chief: Leon SolimanEditorial standards

We do this for everyone who loves this world. The people who have spent their lives in it, and the people just discovering it. Yotters exists so that what we learn belongs to all of them.

Nobody pays us for this. No ads, no sponsors, nothing for sale. We just believe the world is a little better when knowledge is shared instead of kept.

If it gave you something today, tell us to keep going. Follow us, leave a like, or write a positive comment. We read every one, and they are what keeps us going.

Related stories

Refit & Yards

Palumbo Gets 30 Years on 14,200 sq m of Ancona's Burnt Tubimar Site

Refit & Yards

Lloyd Werft Takes a 7-Hectare Site in Bremerhaven on 30-Year Lease

Refit & Yards

Astra Nord's Second Concept in a Year Still Has No Owner

The Yotters Brief

The yacht world, read every morning.

The stories that move the yacht world, before the market does. Join the owners, brokers and builders who start the day with Yotters.