Trinity's Mirabella refit finishes 3 months late, price undisclosed

The 2004 Trinity motor yacht Mirabella left Reviva Refit's Tuzla yard on 15 July, eight and a half months after arriving and three months past the yard's own April target. The overrun and the silence on cost are the two facts an owner needs before booking the same yard, which has quietly become the default address for what is left of Trinity's fleet.
11 August 20264 min readYotters DeskEdited by Leon Soliman
Mirabella alongside at Reviva Refit's Tuzla facility, redelivered 15 July 2026 after an 8.5-month refit that ran three months past the yard's own target.
Mirabella alongside at Reviva Refit's Tuzla facility, redelivered 15 July 2026 after an 8.5-month refit that ran three months past the yard's own target.Photo: SuperYacht Times (press material)

A six-and-a-half month plan became eight and a half

The current owner bought Mirabella in May 2025 and had her at Reviva Refit within four months, a buy-then-rebuild timeline rather than a buy-and-cruise one. Mirabella hauled out at Reviva, the refit division of the Turkish yard Mengi Yay, at the beginning of October 2025, having arrived at the Tuzla facility in mid-September under the project code R15. The yard and the owner's representative had set 15 April 2026 as the delivery date, a six-and-a-half month programme. The yacht was actually redelivered on 15 July 2026, three months later than planned and eight and a half months after the first tools went on board.

Neither Reviva nor the owner's representative, Rob Dolling of Verpeka Dolling Superyachts, has published a reason for the slip. Ramazan Mengi, Reviva's refit operations director, described the scope rather than the delay: "R15 asked for paint, systems, joinery and structural work at once, our people carried all four across the line together." Running four disciplines in parallel rather than in sequence is a common way yards compress a schedule, and it is also a common way one delayed trade drags the other three behind it, which is consistent with a three-month overrun nobody has explained.

The 47.9-metre hull and her tender, freshly repainted. The refit stripped and repainted the hull and superstructure in a climate-controlled shed rather than touching up in place.
The 47.9-metre hull and her tender, freshly repainted. The refit stripped and repainted the hull and superstructure in a climate-controlled shed rather than touching up in place.Photo: SuperYacht Times (press material)

What eight and a half months actually bought

The scope was a full-boat refit, not a cosmetic one. The hull and superstructure were stripped and repainted in a climate-controlled shed. The electrical and electronic infrastructure was substantially renewed, covering bridge electronics, audio-visual systems and interior and exterior lighting. Interior joinery was stripped back and refinished in walnut tones, with new upholstery and furniture throughout the yacht's five staterooms, which sleep 11 guests across four kings and a twin with a pullman berth.

On deck, the swim platform was reconfigured to house an integrated transformer inside a new watertight chamber, a structural modification rather than a bolt-on, and a bespoke Jacuzzi replaced the original on a redesigned sundeck alongside new seating across every deck level. Mirabella's original propulsion, twin 2,250 hp Caterpillar diesels giving 3,500 nautical miles at 12 knots, was not replaced, so the refit bought systems, structure and finish rather than range or speed. The yacht returns to charter service under her existing specification.

The Mirabella name and the Trinity builder's plate on the hull. Trinity Yachts has not launched a new yacht since 2016, leaving owners of its back catalogue without a builder to return to.
The Mirabella name and the Trinity builder's plate on the hull. Trinity Yachts has not launched a new yacht since 2016, leaving owners of its back catalogue without a builder to return to.Photo: SuperYacht Times (press material)

Reviva has become Trinity's yard by default

Trinity Yachts was founded in 1988 by the Olympic sailor John Dane III, building on the hull of what had been Higgins Shipyard, a commercial and military builder dating to the Second World War, at a yard in New Orleans that survived Hurricane Katrina in 2005 and the 2008 downturn before it stopped taking new orders. The company was sold to Harvey Gulf International Marine in 2015 and has not launched a new yacht since 2016. Its roughly three-decade back catalogue, custom yachts including names still active on the brokerage and charter market such as Cocoa Bean, Unbridled and Mine Games, now has no builder to return to for warranty work, spares sourcing or a refit informed by the original build files. Reviva has stepped into that gap, and Mirabella is not the only Trinity hull proving it.

Berthed alongside Mirabella through the same period was Grand Rusalina, a 59.6-metre Trinity delivered in 2006 to an exterior by Geoff Van Aller with an interior by Ricky Smith Designs, sleeping up to 16 guests over a 6,000-nautical-mile range. She was in for her fourth consecutive year of returning to Reviva, this time under project code R11.4 for a mechanical overhaul of her engines and auxiliary machinery alongside a five-year RINA classification survey, plus a full exterior repaint and new upholstery. A 37.4-metre Bering B121 was also mid-refit at the same yard. Reviva states this was its 15th redelivery since the programme began in 2017, formalised under the Reviva name in 2024, which is a specific and checkable claim rather than a marketing figure, though no third party has audited it.

The bespoke Jacuzzi built into the redesigned sundeck, replacing the original as part of the refit's deck-level work.
The bespoke Jacuzzi built into the redesigned sundeck, replacing the original as part of the refit's deck-level work.Photo: SuperYacht Times (press material)
The main saloon after new upholstery and refinished joinery. None of the yacht's five-stateroom, 11-guest layout changed in the rebuild.
The main saloon after new upholstery and refinished joinery. None of the yacht's five-stateroom, 11-guest layout changed in the rebuild.Photo: SuperYacht Times (press material)

What this means for the owner, not just the yard

An owner weighing a yacht from a defunct builder is really weighing two separate questions this refit answers only partly: can the boat be brought current, and can it be done to a schedule you can plan a charter season or an owner's cruise around. Reviva answers the first convincingly, fifteen redeliveries and a repeat Trinity client are a real track record, not a pitch. It answers the second badly. A three-month slip against a published date, with no explanation offered by either the yard or the owner's side, is exactly the kind of risk a buyer needs priced into any refit quote before signing, and it was not priced into this one publicly.

The other gap is money. Nobody involved, not Reviva, not Dolling, not any broker listing tied to the yacht, has published what an eight-and-a-half month, four-discipline refit on a 47.9-metre yacht actually costs, and the brokerage listings for comparable Trinity yachts still on the charter market are silent on it too. For an owner comparing a refit against a new-build order or a younger secondhand yacht, that is the single number that would let the comparison actually be made, and its absence means every prospective Reviva client is negotiating without a public benchmark. Mirabella was too recently redelivered, on 15 July, for any independent owner, charter guest or crew account of the finished result to exist yet; what is published so far comes entirely from the yard's own side.

What is good, and what to watch

Strong points

  • A yard with a real, repeat track record on this exact hull type15 redeliveries since 2017 and a Trinity client, Grand Rusalina, now returning for a 4th consecutive year - owners are voting with repeat business, not just a sales pitch
  • Full-scope work, not a cosmetic refreshstructural swim-platform modification, a full electrical and bridge-electronics renewal and complete joinery refinishing went in alongside the paint, addressing systems as well as looks

What to watch

  • The published schedule slipped three months, unexplainedthe yard's own 15 April target became a 15 July redelivery with no stated cause - a real risk for any owner planning a season around a refit date
  • No price anywhere in publicneither the yard nor the owner's side has disclosed what an 8.5-month, four-discipline refit costs, so a prospective client has no public benchmark to negotiate against

Practical detail

Trinity's Mirabella refit finishes 3 months late, price undisclosed
YachtMirabella, 47.9m/157'2", built 2004 by Trinity Yachts, New Orleans (closed 2016)
Refit durationHaul-out early October 2025 to redelivery 15 July 2026 - 8.5 months, 3 months past the yard's own 15 April target
Engines and rangeTwin 2,250hp Caterpillar diesels, 3,500nm at 12 knots (unchanged by this refit)
Accommodation11 guests across 5 staterooms - 4 king, 1 twin with pullman
CostNot published, by the yard, the owner's representative, or any broker listing - the figure a prospective client would need most
Yard's other current Trinity work59.6m Grand Rusalina, in for a 4th consecutive year (engine and machinery overhaul, 5-year RINA survey); also a 37.4m Bering B121

Questions this story answers

What happened?

The 2004 Trinity motor yacht Mirabella left Reviva Refit's Tuzla yard on 15 July, eight and a half months after arriving and three months past the yard's own April target. The overrun and the silence on cost are the two facts an owner needs before booking the same yard, which has quietly become the default address for what is left of Trinity's fleet.

What is good about it?

A yard with a real, repeat track record on this exact hull type. 15 redeliveries since 2017 and a Trinity client, Grand Rusalina, now returning for a 4th consecutive year - owners are voting with repeat business, not just a sales pitch

What should an owner or buyer watch?

The published schedule slipped three months, unexplained. the yard's own 15 April target became a 15 July redelivery with no stated cause - a real risk for any owner planning a season around a refit date

Who reported this?

BOAT International, Megayacht News, Yacht Kings.

Reported from primary sources: BOAT International, Megayacht News, Yacht Kings.
Yotters DeskEditor-in-Chief: Leon SolimanEditorial standards

We do this for everyone who loves this world. The people who have spent their lives in it, and the people just discovering it. Yotters exists so that what we learn belongs to all of them.

Nobody pays us for this. No ads, no sponsors, nothing for sale. We just believe the world is a little better when knowledge is shared instead of kept.

If it gave you something today, tell us to keep going. Follow us, leave a like, or write a positive comment. We read every one, and they are what keeps us going.

What to expect

Trinity's Mirabella refit finishes 3 months late, price undisclosed
A second saloon seating area with the new furniture the refit specified throughout the interior.
A second saloon seating area with the new furniture the refit specified throughout the interior.Photo: SuperYacht Times (press material)
The bar, refinished in dark joinery, part of the interior work that ran alongside the paint and structural jobs Reviva says drove the schedule to 8.5 months.
The bar, refinished in dark joinery, part of the interior work that ran alongside the paint and structural jobs Reviva says drove the schedule to 8.5 months.Photo: SuperYacht Times (press material)
A media lounge with new sectional seating, one of the interior spaces refreshed during Mirabella's time at the yard.
A media lounge with new sectional seating, one of the interior spaces refreshed during Mirabella's time at the yard.Photo: SuperYacht Times (press material)

Related stories

Refit & Yards

Monaco Gets a Dedicated Refit Show; the Market Numbers Don't Agree

Refit & Yards

Mulder's Delta One Finishes a Refit, Nine Years After Launch

Refit & Yards

A refit process that shows you the 70-metre boat before you sign for it

The Yotters Brief

The yacht world, read every morning.

The stories that move the yacht world, before the market does. Join the owners, brokers and builders who start the day with Yotters.